Project Site and Folder Standard
Tab & Shift Engineering Ltd. · The same structure on every project
| Prepared for | Prepared by | Date | Status |
|---|---|---|---|
| Marcus Chen Chief Operating Officer | Floor 16 Technologies | Oct 2, 2026 | v2.0 · Approved |
Summary
Every project gets the same site with the same five libraries, built by the project register the moment a project is approved. Folders stop at two levels and each one tags what is dropped into it, so people find things on day one because every project looks the same.
Three questions decide where things go
Libraries, folders and columns each do one job. Ask the questions in order and stop at the first yes.
| # | If the answer is yes | Make it | Example |
|---|---|---|---|
| 1 | Does it need different permissions, retention or outside sharing? | A library. This is the only reason to create one. | Commercial is its own library because only the project manager and Finance see fees. |
| 2 | Is it a place people expect to click, where every file shares one value? | A folder with a default value, so it tags on drop. | Design › Structural stamps Discipline = Structural on everything dropped in. |
| 3 | Will people filter, sort or roll it up across projects? | A column. Most things end up here. | Issue State: every drawing issued for construction, across all projects, in one view. |
The project site
One team site per project, joined to the Projects hub so it inherits navigation, search and branding. The tree below is what the register builds, every time. Annotations show what each folder stamps on the files dropped into it.
- Tab & Shift Hubcommunication site · navigation, news, search
- Projects hubevery project site joins it
- P-2214 Highway 9 Interchangeteam site · built by the register
- Project Managementfolders stamp Document Type
- 01 Contract and ScopeType = Contract
- 02 ScheduleType = Schedule
- 03 Budget and CostType = Cost Report
- 04 MeetingsType = Minutes
- 05 ChangesType = Change Order
- 06 Risks and IssuesType = Risk Register
- Designfolders stamp Discipline
- CivilDiscipline = CV
- StructuralDiscipline = ST
- MechanicalDiscipline = ME
- ElectricalDiscipline = EL
- ProcessDiscipline = PR
- No third level. Revisions live in version historyIssue State is a column
- Correspondencefolders stamp Party
- ClientParty = Client
- SubconsultantsParty = Subconsultant
- AuthoritiesParty = Authority
- Fieldfolders stamp Document Type
- Daily ReportsType = Daily Report
- PhotosType = Site Photo
- InspectionsType = Inspection
- SafetyType = Hazard Assessment
- Field ChangesType = Field Change
- Commercialrestricted · PM and Finance only
- ProposalType = Proposal
- Fees and InvoicesType = Invoice
- SubcontractsType = Subcontract
- Client Exchangeonly when needed · guests expire at close
The libraries
| Library | What goes in it | What does not |
|---|---|---|
| Project Management | Contract and scope, schedules, budgets and cost reports, minutes, change orders, the risk register | Fees and invoices (Commercial) |
| Design | Drawings, calculations, specifications, models, datasheets, design reports | Superseded copies saved as new files. Use versions |
| Correspondence | Letters, transmittals and the emails that record a decision, saved as PDF or .msg | Every email. Only the ones that decide something |
| Field | Daily reports, site photos, inspections, hazard assessments, field changes | Equipment records (Field Services site) |
| Commercial | Proposal, fee schedule, invoices, subcontracts and purchase orders | The signed contract (Project Management, read by all) |
| Client Exchange | Copies shared with the client or outside consultants | Originals. They stay in Design |
Naming
Names carry what a person needs to recognize a file in a list. Everything else is a column, so names stay short and nobody types a date in three formats.
| What | Pattern | Example |
|---|---|---|
| Project number | P- and four digits, issued by the register, never typed | P-2214 |
| Site name | Project number and a short name, 40 characters at most | P-2214 Highway 9 Interchange |
| Site address | Project number only, so it never changes when the name does | /sites/P-2214 |
| Controlled documents | Project, discipline, type and sequence. The revision is a column, not part of the name | P-2214-ST-CAL-014 |
| Dated documents | Date first, year-month-day, then the subject | 2026-10-14 Progress Meeting 12 |
| Everything else | A plain description, under 80 characters | Geotechnical report, north abutment |
Never in a name. FINAL, v2, rev, Copy of, initials, dates in any other format, and the characters # % &. Version history keeps every earlier copy, and the Revision and Status columns say which one is current.
Codes
| Discipline | Code | Document type | Code |
|---|---|---|---|
| Civil | CV | Drawing | DWG |
| Structural | ST | Calculation | CAL |
| Mechanical | ME | Specification | SPC |
| Electrical | EL | Datasheet | DSH |
| Process | PR | Report | RPT |
| General | GN | Model | MDL |
Metadata columns
Nine columns, published once from the content type hub so the same word means the same thing on every project. Six fill themselves. The person uploading picks Document Type when the folder has not already set it, and the engineer issuing a drawing sets Revision and Issue State.
| Column | Type | Values | Set by | On |
|---|---|---|---|---|
| Project | Managed metadata, hidden | Project number and name | The site, when it is built | All |
| Client | Lookup | From the client list in the register | The site | All |
| Document Type | Choice, required | 24 types, filtered so each library offers its own | Folder default, or the person uploading | All |
| Discipline | Choice | CV, ST, ME, EL, PR, GN | Folder default | Design, Field |
| Party | Choice | Client, Subconsultant, Authority | Folder default | Correspondence |
| Revision | Text | A, B, C in draft; 0, 1, 2 once issued | The engineer issuing it | Design |
| Issue State | Choice | Issued for Review, Issued for Construction, As-Built, Superseded | The engineer issuing it | Design |
| Status | Choice | Draft, Final | Defaults to Draft | Project Management, Commercial |
| Sensitivity | Purview label | Internal, Confidential | Library default. Commercial is Confidential | All |
Views every Design library opens with
- Current issued. Issue State is Issued for Construction, grouped by Discipline. The view a site team lives in.
- My drafts. Status is Draft and Modified By is me.
- Superseded. Hidden from every other view, so nobody builds from the wrong revision.
Permissions
Permissions are set per library, through four groups per project. No folder ever gets its own permissions; if something needs different access, it gets its own library.
| Library | Project owners | Project team | All staff | Finance | Client guests |
|---|---|---|---|---|---|
| Project Management | Full | Edit | Read | Read | None |
| Design | Full | Edit | Read | None | None |
| Correspondence | Full | Edit | Read | None | None |
| Field | Full | Edit | Read | None | None |
| Restricted Commercial | Full | None | None | Edit | None |
| Client Exchange | Full | Edit | None | None | Edit |
- Project owners are the project manager and the division lead. Two owners on every site, so someone always answers.
- Groups, never named people, on every library. Joining or leaving a project is one change in one group.
- Guests reach Client Exchange only, and their access ends 90 days after it is granted or when the project closes, whichever is first.
Retention
Every library carries a retention label. The clock starts on the close date in the project register, not on the day each file was saved.
| Library | Label | Kept for | At the end |
|---|---|---|---|
| Design | Design Record | 15 years | Disposition review |
| Project Management | Project Record | 10 years | Disposition review |
| Correspondence | Project Record | 10 years | Disposition review |
| Field | Field Record | 10 years | Disposition review |
| Commercial | Financial Record | 7 years | Deleted after review |
| Client Exchange | None: copies only | Until close | Emptied at close |
From approval to disposal
Closing a project in the register is the only step needed to start every retention clock. Nothing is deleted without a signed disposition review.
What the standard does not allow
- A third level of folders. Past two levels a folder is holding a year, a vendor or a phase, and those are columns.
- Folders named for years, people, or Old, Misc, Temp and New folder.
- Permissions on a single folder. Split it into a library instead.
- Project files kept in OneDrive or sent as attachments in Teams chat. Share a link to the file in the project site.
- A library added to one project only. Changes go through the owner of this standard and reach every project.
Ownership and changes
| Version | Date | Change | Approved by |
|---|---|---|---|
| v1.0 | Aug 21, 2026 | First draft from the Scan and eight interviews | Draft |
| v1.1 | Sep 18, 2026 | Pilot changes: Photos folder added to Field; Party column added to Correspondence | Elena Rossi |
| v2.0 | Oct 2, 2026 | Approved for the Move and every new project after it | Marcus Chen |
The Director of Operations owns this standard. Requests for a change go to the owner, are reviewed each quarter, and when approved are pushed to every project site by the register, so no project drifts from the rest.